Retail stores & commercial showrooms

In retail the calendar is the budget. Every week between possession and opening is rent without revenue — so the landlord’s criteria, the storefront and the permit path are planned from day one.

Apparel showroom with hanging garment racks, white plinths and linear lighting

2026 retail build-out benchmarks

ScopeBenchmark
Retail store / showroom build-out$100 – $225 / SF
Light refresh of an existing store$50 – $100 / SF
Architectural & MEP design fees$8 – $12 / SF (8% – 10%)
Municipal permit & plan review$1.50 – $5.00 / SF

Source: Meade Design 2025–2026 U.S. fit-out benchmarks.

Planning a retail TI

Group M occupant load

Sales floors are calculated at 30 SF gross per occupant on the grade floor under IBC 2018 (IBC Table 1004.5; IBC 2021 uses 60 SF gross). A 3,000 SF store at 30 SF is 100 occupants — two exits, and restroom counts under IBC Table 2902.1. Stock rooms are calculated separately at 300 SF gross.

Landlord tenant criteria manuals

Shopping centers and mixed-use landlords publish tenant criteria: storefront setbacks and materials, neutral-pier treatment, signage size and illumination, ceiling heights, rooftop equipment screening and approved contractors. Landlord design review usually runs before or alongside the municipal permit — schedule both.

Storefront and signage

A new storefront involves the landlord’s structural and envelope rules, energy code glazing limits, accessible entrance hardware and, often, a separate sign permit. Coordinate the sign band, blocking and power in the architectural set so signage installs before opening day.

Lighting power and controls

Retail lighting is held to an interior lighting power allowance under ASHRAE 90.1 or the IECC, with additional allowances for display lighting. Plan accent lighting into the allowance rather than discovering the limit at plan check.

Controlling the rent-commencement clock

  1. Negotiate the trigger. Rent commencement tied to “the earlier of opening or X days after delivery” makes permit time your cost — request permit-contingent extensions in the LOI.
  2. Submit to the landlord early. Criteria-manual review often takes 2–4 weeks before a municipal submittal can be signed.
  3. Order long-lead items from the permit set. Storefront systems, signage and rooftop units routinely run 8–12 weeks.
  4. Phase the permit where allowed. Demolition or a separate storefront permit can start construction while interiors are in review.

Budget a retail build-out against the allowance in the LOI.