Comparison

Design-bid-build vs. design-build for tenant improvements

The delivery method decides who holds the drawings, who carries the price risk and how much time sits between lease signing and opening day.

Contractor finishing drywall in a commercial interior under construction
DBB

Design-bid-build

The tenant hires the architect, who completes the permit set. Two to four general contractors bid the same documents; the tenant signs with the best-value GC. Architect and contractor are separate contracts with the tenant.

DB

Design-build

One contract with a design-build contractor who employs or subcontracts the architect and engineers. Pricing develops with the design, often as a guaranteed maximum price (GMP) once drawings are far enough along.

Side-by-side

 Design-bid-buildDesign-build
ScheduleSequential: design → bid (2–4 weeks) → constructionOverlapping: pricing, permitting and long-lead procurement start during design — often 3–6 weeks faster
Price competitionStrong — several GCs bid identical, complete documentsLimited — competition happens on fee and general conditions, or not at all
Architectural controlThe architect works for the tenant and reviews the GC’s workThe designer works for the builder; value engineering can quietly change scope
Change-order exposureGaps in documents become change orders; complete permit sets keep them lowFewer design-error change orders, but a GMP carries contingency you pay for
Single point of responsibilityNo — design and construction are separateYes — one contract for both
Best forLarger or complex build-outs, tenants who want price certainty from competitive bidsSmall, repeatable suites, tight rent-commencement dates, owners with a trusted builder

Suites under 5,000 SF

Small office and retail TIs are often simple enough that design-build’s speed outweighs the loss of bid competition — especially second-generation suites where the scope is mostly finishes, lighting and a few walls. Ask for an open-book GMP and keep an independent test fit as the scope baseline.

Larger or complex build-outs

Above roughly 5,000 SF — or in any restaurant, clinic or cold-shell project — the dollars at stake make competitive bidding on a complete, coordinated permit set worth the extra weeks. Complete documents are also what keep change orders under control once construction starts.

A hybrid that works for many tenants

Bring a GC in during design development under a preconstruction agreement to price the schematic layout, flag long-lead items and check constructability — then finish the permit set independently and either negotiate with that GC or bid it. You keep the architect on your side, gain the schedule benefit of early pricing, and preserve the option to compete the work.

See what a complete permit set contains, or compare who the architect works for.